The Tomorrowland project of the Shanghai Disneyland is located in the southwest corner of the park. In order to achieve the scheduled construction period, the internal partition wall was intended to be constructed at the same time as the MEP installation, so we adopted our ring lock scaffolding. The scaffolding needs to provide an operation platform with an elevation of 9m, an operation platform around the bridleway and a construction operation space of about 30cm away from the partition wall for the construction of the inner wall. Stairs, bridleway, and amusement tracks have already been finished, so we need to avoid these facilities. The volume of this project is 9500m³, and the construction period is expected to be 15 days.

We use our type B ring lock scaffolding for this project, with steel plank, steel stair and steel toeboard.
The main spacing of the standard is 2m×2m, and the vertical step distance is 1.5m. The special steel planks are laid on the working face as the operating platform.
The main problems solved by us are as follows:
1. Providing a 9m length construction operation platform for roof spraying and installation of MEP. Steel planks are covered at the place where the horizontal bar arrangement is relatively regular.
2. The around steel beam needs to be sprayed, so the around area needs to have a working face. The around working face is full of steel planks.
3. Providing space for the construction of the internal partition and construction platform, the partition wall construction is divided into two working procedures. This scaffolding of this area will has large distance from the wall, so after we finish loading the steel planks, we will use a steel pipe & coupler for local supplement(see the wall frame drawing );
4. Providing a working surface for the spraying of the steel column in this area. The design didn’t specifically consider the operating surface of the steel column, so we need to use our scaffold as the main force system, and set up the operating surface with a steel pipe & coupler and a wooden plank on the scaffold.
5. Two staircases are provided, and access is provided at the ground entrance.
Carry empty processing
When scaffolding is erected, each component should avoid the lower amusement track and leave operating space for the construction of the inner partition wall. The inner partition wall is constructed to the elevation of about 7.5m, and the upper part has space to use the empty member.The operation scaffolding is carried out using 4m or 6m truss components, 16 I-steel and steel pipes, etc.
When the truss pieces are in use, the wedges at both ends should be tightened, and ledgers should be erected to the direction of the truss pieces to prevent the truss pieces from being unstable(as shown in Figure 7).